We are a General Engineering and Electrical Contractor.
Our firm employs a skilled work force comprised of General Laborers, Masons, Equipment
Operators and Electricians. Our license has classifications of A and C10.
We work in the public and private sectors. We have
performed work for Municipalities, School Districts, Ports and Developers.
Below are some of our completed projects:
(Project Name, Owner, Sub or Prime Contractor, Contract Amount,
Brief Description)
 | Port of Oakland - Contract C
 | Port of Oakland |
 | Subcontractor |
 | $644,000.00 |
 | Installation of new and remove and replace multiple
traffic signal systems. |
|
 | LaSalle Liggett Underground Utility
 | City of Oakland |
 | Prime Contractor |
 | $604,000.00 |
 | Installation of primary and secondary service laterals
for PG&E, Pacbell and AT&T |
|
 | San Leandro High School Upgrades
 | San Leandro Unified School District |
 | Prime Contractor |
 | Time and Material $53,500.00 |
 | Repair and installation of electrical conduits, pull
boxes, circuits and distribution panels. |
|
 | Witter Field
 | Piedmont Unified School District |
 | Subcontractor |
 | $510,000.00 |
 | Installation of underground conduits, site and
outbuilding lighting, four 120' light standards, communication and fire
alarm systems. |
|
 | City of Oakland - RSTOP, #H4301
 | City of Oakland |
 | Prime Contractor |
 | $550,000.00 |
 | Modify 45 traffic signal intersections, which totaled
approximately 12,000 LF of trenching. |
|
 | Swans Market
 | Oliver & Co. |
 | Subcontractor |
 | $135,000.00 |
 | Installation of primary and secondary conduits, boxes,
circuits, switchgear and related feeders, street lighting and traffic
signal system. |
|
Please contact us for any and all of your